Together we build bridges: in Delft (The Netherlands) it was a challenge to adapt the bridge “St. Sebastiaansbrug”. The Pile Pusher Pro proved to be the right choice. The vibration-free and, above all, consistent foundation of the precast concrete piles was an indispensable addition to the projec. In total, no fewer than 420 foundation piles have been pushed into the soil with a total length of approximately 8400 m.

 

Project description – Pile Pusher Pro

  • Client: Van Spijker
  • Total pushed meters: approx. 8.400 m
  • Number of precast concrete piles: 420
  • Pile length: 22 m
  • Realisation: 2019

 